How scheduling works in MS Project
Author: mety Labels:: How scheduling works in MS ProjectMicrosoft Office Project uses a powerful scheduling engine to help align your organization's projects and tasks (task: An activity that has a beginning and an end. Project plans are made up of tasks.) with available resources (resources: The people, equipment, and material that are used to complete tasks in a project.). Understanding how Project schedules work is a key factor in making intelligent planning decisions Project schedules a project from the information that you enter about the following:
For each task, you might enter one or all of the following:
You can enter resources in your project and then assign them to tasks to indicate which resource is responsible for completing each assignment (assignment: A specific resource that is assigned to a particular task.). Not only does this help you plan project staffing, it can also help you to calculate the number of machines needed or the quantity of material to be consumed. If you enter resources, task schedules are further refined according to the following resource information:
How does the project start date affect the schedule?If you enter a start date for the project, by default, Project schedules tasks to begin on the project's start date and calculates the project's finish date (finish date: The date that a task is scheduled to be completed. This date is based on the task's start date, duration, calendars, predecessor dates, task dependencies, and constraints.) based on the last task to finish. As you enter more information about tasks, such as task dependencies, durations, and constraints, Project adjusts the schedule to reflect more accurate dates for tasks.When you create a new project, you first enter the project's start date. When you schedule a project from the start date, all tasks start at the project start date unless you specify otherwise. With no task dependencies or constraints applied, the project's duration is the same as the duration of the longest task. In other words, the project finish date is the same as the longest task's finish date. Task dependencies, such as the finish-to-start dependency between the first and second tasks (as shown here), can change the project's finish date. Nearly all projects should be scheduled from a known start date. Even if you know the date that a project must be completed, scheduling from a start date gives you the maximum flexibility. However, you might want to schedule from a finish date when:
What are the default settings for calculating the schedule?Project calculates the duration of tasks based on the definitions of the duration units on the Calendar tab of the Options dialog box (Tools menu). Just like a normal monthly calendar, the year begins in January and each week begins on Sunday or Monday. By default, when Project calculates duration units, one day equals 8 hours, one week equals 40 hours, and one month equals 20 working days. If you enter start and finish dates for tasks and don't enter start and finish times, Project uses 8:00 A.M. as the default start time and 5:00 P.M. as the default end time.How do constraints affect the schedule?When you need to control the start or finish date of a task, you can change the constraint on the task. Flexible constraints (flexible constraint: A constraint that is flexible and does not tie a task to a single date. Flexible constraints are As Soon As Possible, As Late As Possible, Finish No Earlier Than, Finish No Later Than, Start No Earlier Than, and Start No Later Than.) work with task dependencies to make a task occur as soon or as late as the task dependency will allow. For example, a task with an As Soon As Possible (ASAP) constraint and a finish-to-start dependency will be scheduled as soon as the predecessor task finishes. By default, all tasks in a project that is scheduled from the start date have the ASAP constraint applied. Likewise, by default, all tasks in a project that is scheduled from the finish date have the As Late As Possible (ALAP) constraint applied.Constraints with moderate scheduling flexibility will restrict a task from starting or finishing before or after a date you choose. For example, a task with a Start No Earlier Than (SNET) constraint for June 15 and a finish-to-start dependency to another task can begin June 15 if its predecessor is finished by June 15 (or later if its predecessor finishes after June 15), but it can't be scheduled before June 15. With the default finish-to-start task relationship and an ASAP constraint applied to these tasks, the successor task (the second one) is scheduled to begin as soon as the predecessor task (the first one) is scheduled to finish. With a SNET constraint applied, the successor task cannot begin before the constraint date, even if (as shown here) the predecessor task is completed before the constraint date. Inflexible constraints (inflexible constraint: A constraint that is inflexible because it ties a task to a date. The inflexible constraints are Must Finish On and Must Start On.) override any task dependencies by default and restrict a task to a date you choose. For example, a task with a Must Start On (MSO) constraint for September 30 and a finish-to-start dependency to another task will always be scheduled for September 30 no matter whether its predecessor finishes early or late. If a task that is constrained to a date has a predecessor that finishes too late for the successor to begin on the date specified in the constraint, negative slack (slack: The amount of time that a task can slip before it affects another task or the project's finish date. Free slack is how much a task can slip before it delays another task. Total slack is how much a task can slip before it delays the project.) can occur. To review or change the constraint on a task, select the task, click Task Information , and then click the Advanced tab. Constraint information is in the Constraint type and Constraint date boxes. How do deadline dates affect the schedule?Deadline dates (deadline: A target date indicating when you want a task to be completed. If the deadline date passes and the task is not completed, Project displays an indicator.) don't usually affect task scheduling. They are used to indicate a target date you don't want to miss, without requiring you to set a task constraint that could affect scheduling if predecessor (predecessor: A task that must start or finish before another task can start or finish.) tasks change. A task with a deadline is scheduled just like any other task, but when a task finishes after its deadline, Project displays a task indicator (indicators: Small icons representing information for a task or resource that are displayed in the Indicators field. The Indicators field is located to the right of the ID field and appears in a number of tables.) notifying you that the task missed its deadline.Deadline dates can affect the total slack on tasks. If you enter a deadline date before the end of the task's total slack, total slack will be recalculated by using the deadline date rather than the task's late finish date. The task becomes critical if the total slack reaches zero. You can set deadlines for summary tasks (summary task: A task that is made up of subtasks and summarizes those subtasks. Use outlining to create summary tasks. Project automatically determines summary task information [such as duration and cost] by using information from the subtasks.) as well as individual tasks. If the summary task's deadline conflicts with any of the subtasks (subtask: A task that is part of a summary task. The subtask information is consolidated into the summary task. You can designate subtasks by using the Project outlining feature.), the deadline indicator signifies a missed deadline among the subtasks. But deadline dates can affect how tasks are scheduled if you set a deadline date on a task with an As Late As Possible (ALAP) constraint. The task is scheduled to finish on the deadline date, though the task could still finish after its deadline if its predecessors slipped. To review or change a task deadline, select the task, click Task Information , and then click the Advanced tab. Use the Deadline box. How do calendars affect the schedule?Calendars determine the standard working time (working time: Hours designated in a resource or project calendar during which work can occur.) and nonworking time (nonworking time: Hours or days designated in a resource or project calendar when Project should not schedule tasks because work is not done. Nonworking time can include lunch breaks, weekends, and holidays, for example.), such as weekends and holidays, for the project. They are used to determine the resource availability, how resources that are assigned to tasks are scheduled, and how the tasks themselves are scheduled. Project and task calendars are used in scheduling the tasks, and if resources are assigned to tasks, resource calendars are used as well.The calendars referred to in Project are:
How do resource assignments drive the schedule?If you don't assign resources to tasks in your project, Project calculates the schedule using durations, task dependencies, constraints, and project and task calendar information. If you do assign resources, the tasks are also scheduled according to resources' calendars and assignment units (assignment units: The percentage of a work resource's time, or units, that the resource is assigned to a task.), providing for more accurate scheduling.An assignment is the association of a specific task with a specific resource that is responsible for completing the task. More than one resource can be assigned to a task. Work resources (work resource: People and equipment resources that perform work to accomplish a task. Work resources consume time [hours or days] to accomplish tasks.), material resources (material resource: The supplies or other consumable items that are used to complete tasks in a project.), and cost resources (cost resources: Resources that don't depend on the amount of work on a task or the duration of a task, such as airfare or lodging.) can be assigned to tasks. Unlike work resources, assigning material resources or cost resources to a task does not affect task scheduling. For example, in your project you have a task named Develop specifications. You also have an engineering resource, Sean. If you assign Sean to the Develop specifications task, the scheduling of this task depends on Sean's resource calendar and assignment units, in addition to task information such as duration, task dependencies, constraints, and calendars. In addition to scheduling according to task information, after you assign resources to the tasks in your project, Project has resource and assignment information to use in calculating schedule information, including:
What information can help me analyze my project's progress?Five pieces of task information help you analyze progress as you track tasks in your project: duration, work, start date, finish date, and cost.Variations of each of these types of fields help you compare and evaluate your progress: planned (plan: A schedule of task start and finish dates and resource and cost data. A baseline plan is the original plan that you save and use to monitor progress. An interim plan is a set of dates you save during the project to compare to other interim plans.), scheduled (scheduled: The most current information about a project, including actual and remaining dates, durations, and costs for tasks that have started and the latest projected dates, durations, and costs for tasks that have not yet started.), actual (actual: Information that shows what has actually occurred. For example, the actual start date for a task is the day that the task actually started.), and remaining (remaining work: The amount of work, in terms of a time unit such as hours or days, that is left to be completed on a task. This is calculated as follows: Remaining Work = Work - Actual Work.). For example, for one task, there can be fields of information containing planned work, scheduled work, actual work, and remaining work. The contents of these fields might match one another, or they might all be different. Variances (variance: The difference between baseline and scheduled task or resource information, they usually occur when you set a baseline plan and begin entering actual information into your schedule. Variances can occur in work, costs, and schedule.) between certain fields can also be examined for useful tracking information. For this reason, these fields are referred to as tracking fields.
|